Taylor Technology Campus
A developer campus by Big Watt Digital + PowerHouse Data Centers in Taylor (Williamson County), TX, on the ERCOT grid. Status: approved.
Grid and gas impact
At full buildout this campus is announced at 1,000 MW. After phasing to 2030 and weighting by build stage, the index expects about 650 MW running by 2030. That is about 0.7% of the ERCOT record peak of July 22, 2026 (91,089 MW).
At that level it would use about 4,270 GWh of electricity a year, roughly what 396,000 US homes use (EIA average of about 10,800 kWh per home), and add about 107.3 MMcf/d of natural gas burn on an average day, counting both on-site generation and the region's gas-fired power plants.
Its rating is driven by gas: most or all of its power comes from on-site or dedicated gas generation, so the strain falls on pipelines and local gas supply rather than the transmission grid. Rated 4 of 4 bolts. Outlined bolts mean the campus is approved, announced or proposed and may not be built as planned.
Latest update. New Nov 3, 2026: Taylor council annexed the 664-acre site and approved a development agreement 5–0 on Oct 8, 2026. Off the ERCOT grid; first power H1 2028.
Fact sheet
- Index ID
- DC-087
- Campus
- Taylor Technology Campus
- Developer / tenant
- Big Watt Digital + PowerHouse Data Centers
- Segment
- Developer campus
- Location
- Taylor (Williamson County), TX
- State / province
- Texas
- Country
- United States
- Metro
- Austin
- Grid region
- ERCOT
- Electric utility
- Off-grid / on-site
- Status
- Approved (counts 65% toward 2030)
- Online / target
- H1 2028
- Announced capacity
- 1,000 MW (Reported (unspecified))
- Expected load by 2030
- 650 MW (index estimate)
- Annual energy at expected load
- about 4,270 GWh
- Power supply
- On-site gas (behind the meter)
- Added gas burn, average day
- 107.3 MMcf/d (index estimate)
- Impact rating
- (4 of 4; scale)
- Confidence
- B (Several consistent sources)
- Last reviewed
- November 3, 2026
Sources
- Big Watt Digital and PowerHouse announce planning approval for Taylor Technology CampusBusiness Wire via Yahoo Finance · Oct 9, 2026Company statement
- Taylor annexes data center site and power plantKUT (Austin NPR) · Oct 9, 2026
- Taylor approves 1 GW gas-fired data center campus for Big Watt and PowerHouseBaxtel · Oct 15, 2026
Every source used across the index is listed in the source log. Spotted an error? Email [email protected] with "Correction: DC-087" in the subject.
How to cite
Data Center Index (datacenterindex.info), Discovery Energy. "Taylor Technology Campus" (DC-087), https://datacenterindex.info/campuses/dc-087-taylor-technology-campus/, updated November 3, 2026.