United States · state
Data centers in Georgia
3 tracked campuses of 100 MW or more in Georgia, on the Southeast utilities grid. The largest expected load by 2030 is OpenAI Project Camellia.
Campuses3100 MW or more
Announced5,676 MWAt full buildout
Expected by 20301,582 MWWeighted by build stage
Gas burn155 MMcf/dAverage day
Campuses in Georgia
| Campus | Location | Grid region | Status | Announced MW | Expected MW 2030 | Power supply | Gas MMcf/d | Impact | Conf. |
|---|---|---|---|---|---|---|---|---|---|
| OpenAI Project CamelliaOpenAI · DC-033 | Effingham County, GA | Southeast utilities | Approved | 3,210 | 626 | Grid (Georgia Power) | 61.2 | B | |
| Microsoft Fairwater AtlantaMicrosoft · DC-009 | Fayetteville, GA | Southeast utilities | Operating, expanding | 636 | 572 | Grid | 55.9 | C | |
| Project BunkhouseTaurus / Digital Realty · DC-052 | Stilesboro, GA | Southeast utilities | Announced | 1,830 | 384 | Not disclosed | 37.6 | C |
Expected load and gas burn are index estimates. See the methodology and the source log.