United States · state
Data centers in Kentucky
2 tracked campuses of 100 MW or more in Kentucky, on the PJM, Southeast utilities grids. The largest expected load by 2030 is Paducah GDP AI Campus.
Campuses2100 MW or more
Announced3,800 MWAt full buildout
Expected by 2030558 MWWeighted by build stage
Gas burn51 MMcf/dAverage day
Campuses in Kentucky
| Campus | Location | Grid region | Status | Announced MW | Expected MW 2030 | Power supply | Gas MMcf/d | Impact | Conf. |
|---|---|---|---|---|---|---|---|---|---|
| Paducah GDP AI CampusBrookfield / NextEra · DC-056 | Kevil, KY | Southeast utilities | Announced | 1,800 | 378 | Not disclosed | 36.9 | C | |
| Rubix Project AshlandRubix Data Centers · DC-045 | Russell, KY | PJM | Proposed | 2,000 | 180 | Not disclosed | 14.1 | D |
Expected load and gas burn are index estimates. See the methodology and the source log.