United States · state

Data centers in Ohio

4 tracked campuses of 100 MW or more in Ohio, on the PJM grid. The largest expected load by 2030 is PORTS Technology Campus.

Campuses4100 MW or more
Announced14,000 MWAt full buildout
Expected by 20304,740 MWWeighted by build stage
Gas burn383 MMcf/dAverage day

Campuses in Ohio

CampusLocationGrid regionStatusAnnounced MWExpected MW 2030Power supplyGas MMcf/dImpactConf.
PORTS Technology CampusSB Energy / SoftBank (New Day Data Centers) · DC-021Piketon, OHPJMUnder construction10,0002,400Not disclosed187.6Grid + gasC
Meta PrometheusMeta · DC-080New Albany, OHPJMOperating, expanding1,000900Grid + on-site gas82.9Grid + gasB
AWS Project GalaxyAmazon · DC-065Sidney, OHPJMUnder construction1,500720Grid56.3GridC
Stargate LordstownOpenAI / SoftBank / Oracle · DC-066Lordstown, OHPJMUnder construction1,500720Not disclosed56.3GridC

Expected load and gas burn are index estimates. See the methodology and the source log.