United States · state
Data centers in Ohio
4 tracked campuses of 100 MW or more in Ohio, on the PJM grid. The largest expected load by 2030 is PORTS Technology Campus.
Campuses4100 MW or more
Announced14,000 MWAt full buildout
Expected by 20304,740 MWWeighted by build stage
Gas burn383 MMcf/dAverage day
Campuses in Ohio
| Campus | Location | Grid region | Status | Announced MW | Expected MW 2030 | Power supply | Gas MMcf/d | Impact | Conf. |
|---|---|---|---|---|---|---|---|---|---|
| PORTS Technology CampusSB Energy / SoftBank (New Day Data Centers) · DC-021 | Piketon, OH | PJM | Under construction | 10,000 | 2,400 | Not disclosed | 187.6 | C | |
| Meta PrometheusMeta · DC-080 | New Albany, OH | PJM | Operating, expanding | 1,000 | 900 | Grid + on-site gas | 82.9 | B | |
| AWS Project GalaxyAmazon · DC-065 | Sidney, OH | PJM | Under construction | 1,500 | 720 | Grid | 56.3 | C | |
| Stargate LordstownOpenAI / SoftBank / Oracle · DC-066 | Lordstown, OH | PJM | Under construction | 1,500 | 720 | Not disclosed | 56.3 | C |
Expected load and gas burn are index estimates. See the methodology and the source log.