United States · state

Data centers in West Virginia

3 tracked campuses of 100 MW or more in West Virginia, on the PJM grid. The largest expected load by 2030 is Nscale Monarch Compute Campus.

Campuses3100 MW or more
Announced6,400 MWAt full buildout
Expected by 20301,313 MWWeighted by build stage
Gas burn118 MMcf/dAverage day

Campuses in West Virginia

CampusLocationGrid regionStatusAnnounced MWExpected MW 2030Power supplyGas MMcf/dImpactConf.
Nscale Monarch Compute CampusNscale · DC-051Point Pleasant, WVPJMUnder construction2,000960Not disclosed75.1GridC
Fundamental Data RidgelineFundamental Data · DC-050Hambleton, WVPJMProposed2,000180Not disclosed14.1GridD
Adams Fork Data Center Energy CampusTransGas Development Systems · DC-040Wharncliffe, WVPJMProposed2,400173On-site gas28.5GasD

Expected load and gas burn are index estimates. See the methodology and the source log.