Campus profile · DC-036

Google Project Tembo

A hyperscale campus by Google in Cheyenne, WY, on the West: Mountain/Northwest grid. Status: under construction.

Announced2,700 MWCampus potential
Expected by 20301,296 MWWeighted by build stage
Gas burn84.4 MMcf/dAverage day
Impact rating4 of 4Grid driven

Grid and gas impact

At full buildout this campus is announced at 2,700 MW. After phasing to 2030 and weighting by build stage, the index expects about 1,296 MW running by 2030.

At that level it would use about 8,515 GWh of electricity a year, roughly what 789,000 US homes use (EIA average of about 10,800 kWh per home), and add about 84.4 MMcf/d of natural gas burn on an average day, counting both on-site generation and the region's gas-fired power plants.

Its rating is driven by grid load: power is expected to come mostly from the utility grid, so the effect shows up in transmission, capacity and generation needs, and in the gas burned by the region's power plants. Rated 4 of 4 bolts. Solid bolts mean the campus is operating or under construction.

Research note. Formerly Project Jade.

Fact sheet

Index ID
DC-036
Campus
Google Project Tembo
Developer / tenant
Google
Segment
Hyperscale
Location
Cheyenne, WY
State / province
Wyoming
Country
United States
Metro
Cheyenne
Grid region
West: Mountain/Northwest
Electric utility
TBD
Status
Under construction (counts 80% toward 2030)
Online / target
Not disclosed
Announced capacity
2,700 MW (Campus potential)
Expected load by 2030
1,296 MW (index estimate)
Annual energy at expected load
about 8,515 GWh
Power supply
Not disclosed
Added gas burn, average day
84.4 MMcf/d (index estimate)
Impact rating
Grid (4 of 4; scale)
Confidence
C (One secondary source)
Last reviewed
November 3, 2026

Sources

Every source used across the index is listed in the source log. Spotted an error? Email [email protected] with "Correction: DC-036" in the subject.

How to cite

Data Center Index (datacenterindex.info), Discovery Energy. "Google Project Tembo" (DC-036), https://datacenterindex.info/campuses/dc-036-google-project-tembo/, updated November 3, 2026.