1 tracked campus of 100 MW or more in Tennessee, on the Southeast utilities grid. The largest expected load by 2030 is xAI Colossus 1 + 2.
Campuses1100 MW or more
Announced1,000 MWAt full buildout
Expected by 2030900 MWWeighted by build stage
Gas burn149 MMcf/dAverage day
Campuses in Tennessee
| Campus | Location | Grid region | Status | Announced MW | Expected MW 2030 | Power supply | Gas MMcf/d | Impact | Conf. |
|---|---|---|---|---|---|---|---|---|---|
| xAI Colossus 1 + 2xAI · DC-004 | Memphis / Southaven, TN | Southeast utilities | Operating, expanding | 1,000 | 900 | Grid + on-site gas | 148.6 | B |
Expected load and gas burn are index estimates. See the methodology and the source log.